During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The...

60.1K

Verified Solution

Question

Accounting

During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$373,700 $902,000 $1,070,000

Estimated costs to complete

636,300 198,000 0

Billings to date

303,000 899,000 1,620,000

Collections to date

273,000 807,000 1,412,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$enter a dollar amountenter a dollar amount

image

Gross profit recognized in 2021

$enter a dollar amountenter a dollar amount

image

Gross profit recognized in 2022

$enter a dollar amountenter a dollar amount

image

Prepare the journal entries to record profit or loss, if any using the percentage-of completion-method and (B) the completed- contract method

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students