During 2020, Culver Company started a construstion job with a contract price of $1,620,000. ...

50.1K

Verified Solution

Question

Accounting

During 2020, Culver Company started a construstion job with a contract price of $1,620,000. The job was completed in 2022. The following information is available.
202020212022
Costs insurred to date $444,400 $867,420 $1,060,000
Estimated costs to complete $565,600 $230,580 $0
Billings to date 301,000904,0001,620,000
Collecions to date 272,000814,0001,411,000
(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completiion metnod is used.
Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $
(b)
(c)

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students