During 2017, Blue Bird Company started a construction job with a contract price of $1,824,000....

60.1K

Verified Solution

Question

Accounting

During 2017, Blue Bird Company started a construction job with a contract price of $1,824,000. The job was completed in 2019. The following information is available. The contract is non-cancellable.

image

Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

image

2019 $456,000 $940,500 $1,219,800 0 Billings to date (non-refundable) 342,000 1,026,000 1,824,000 307,800 923,400 1,624,500 2017 2018 Costs incurred to date Estimated costs to complete 684,000 313,500 Collections to date

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students