During 2017, Blue Bird Company started a construction job with a contract price of $1,824,000....
60.1K
Verified Solution
Question
Accounting
During 2017, Blue Bird Company started a construction job with a contract price of $1,824,000. The job was completed in 2019. The following information is available. The contract is non-cancellable.
Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
2019 $456,000 $940,500 $1,219,800 0 Billings to date (non-refundable) 342,000 1,026,000 1,824,000 307,800 923,400 1,624,500 2017 2018 Costs incurred to date Estimated costs to complete 684,000 313,500 Collections to date
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.