Direct labor variance La Batre Bicycle company manufactures commuter bicycles from recycled materials. The following...
70.2K
Verified Solution
Question
Accounting
Direct labor variance
La Batre Bicycle company manufactures commuter bicycles from recycled materials. The following data for july of the current year are available:
Quantity of direct labor used 760 hr
Actual rate for direct labor. $11.2 per hr.
Bicycles completed in April. 360 bicycles
Standard direct labor per bicycle. 2 hrs.
standard rate for direct labor. $11.4 per hr.
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavaroable variance as a positive number:
direct labor rate variance. $. Favorable/unfavorable
direct labor time variance. $. Favorable/Unfavorable
total direct labor Cost Variance. $. Favorable/Unfavorable
b. How much direct labor should be debited to work in process?
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.