Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend...

50.1K

Verified Solution

Question

General Management

  1. Develop a Gantt Chart based on Table below.
  2. On the same Gantt chart, use a legend to show the project planand the (actual) project progress.
  3. Discuss the significance of the two paths or what they mean tothe project.
Activityimmediate predecessorsnormal timebudgetorganizational unitpercent complete
A-4$90U1100
BA2$35U2100
CA6$75U240
DB3$60U180
EC10$80U10
F-2$40U2100
GF5$55U150
HF7$80U2100
ID,E,G1$40U20
JH10$100U10

Answer & Explanation Solved by verified expert
3.6 Ratings (555 Votes)
Gantt chart is followingResource loading chartActual progress is shown on the Gantt chart as belowCompletion status is indicated by green color barFour alternative paths in the project and their respectiveduration are    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students