DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

50.1K

Verified Solution

Question

Accounting

DataSpan, Inc., automated its plant at the start of the currentyear and installed a flexible manufacturing system. The company isalso evaluating its suppliers and moving toward Lean Production.Many adjustment problems have been encountered, including problemsrelating to performance measurement. After much study, the companyhas decided to use the performance measures below, and it hasgathered data relating to these measures for the first four monthsof operations.

Month
1234
Throughput time (days)????
Delivery cycle time (days)????
Manufacturing cycle efficiency (MCE)????
Percentage of on-time deliveries82%77%74%71%
Total sales (units)3830366734793347

Management would like to know the company's throughput time,manufacturing cycle efficiency, and delivery cycle time. The datato compute these measures have been gathered and appear below:

Average per Month (in days)
1234
Move time per unit0.80.50.60.6
Process time per unit2.32.22.12.0
Wait time per order before start
of production
24.26.329.031.4
Queue time per unit4.45.05.76.5
Inspection time per unit0.91.11.10.9
Requirement 1:
(a)Compute the throughput time for each month. (Round youranswers to 1 decimal place.)
1234
Total throughput time_________   ___________________________
(b)

Compute the manufacturing cycle efficiency (MCE) for each month.(Round your answers to 1 decimal place. Omit the "%" signin your response.)

1234
Manufacturing cycle efficiency (MCE)_________%_________%_________%_________%
(c)Compute the delivery cycle time for each month. (Roundyour answers to 1 decimal place.)
1234
Total delivery cycle time____________________________________
Requirement 2:
Refer to the move time, process time, and so forth,given above for month 4.
(a)

Assume that in month 5 the move time, process time, and soforth, are the same as in month 4, except that through the use ofLean Production the company is able to completely eliminate thequeue time during production. Compute the new throughput time andMCE. (Round your answers to 1 decimal place. Omit the "%"sign in your response.)

Total throughputtime                     _________
Manufacturing cycle efficiency (MCE) _________%
(b)

Assume in month 6 that the move time, process time, and soforth, are again the same as in month 4, except that the company isable to completely eliminate both the queue time during productionand the inspection time. Compute the new throughput time and MCE.(Round your answers to 1 decimal place. Omit the "%" signin your response.)

Total throughput time       _________
Manufacturing cycle efficiency (MCE)    _________%

requirement 3

3-a. (Month 5) Refer to the move time, process time, and soforth, given for month 4. Assume that in month 5 the move time,process time, and so forth, are the same as in month 4, except thatthrough the use of Lean Production the company is able tocompletely eliminate the queue time during production. Compute thenew throughput time and MCE.

3-b. (Month 6) Refer to the move time, process time, and soforth, given for month 4. Assume in month 6 that the move time,process time, and so forth, are again the same as in month 4,except that the company is able to completely eliminate both thequeue time during production and the inspection time. Compute thenew throughput time and MCE.

(Round your answers to 1 decimal place.)

Show less

Month 5Month 6
Throughput timedaysdays
Manufacturing cycle efficiency (MCE)%%

Answer & Explanation Solved by verified expert
4.1 Ratings (595 Votes)
Ans 3Month 5Month 6Throughput time35 days26 daysManufacturing cycle efficiency    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students