Crane has a standard of 2 hours of labor per unit, at $12 per hour....

50.1K

Verified Solution

Question

Accounting

image
image
Crane has a standard of 2 hours of labor per unit, at $12 per hour. In producing 1600 units, Crane used 2850 hours of laborat a total cost of $34770.Crane's labor quantity variance is $570U. $570F $4200 $4270F Current Attempt in Progress The per-unit standards for direct laborare 1.5 direct labor hours at $15 per hour. If in producing 1700 units, the actual direct labor cost was $30225 for 1950 direct labor hours worked, the total direct labor variance is $1700 unfavorable $8025 favorable $6075 unfavorable $8025 unfavorable

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students