Cost of Production Report
The Cutting Department of Karachi Carpet Company provides thefollowing data for January. Assume that all materials are added atthe beginning of the process.
Work in process, January 1, 10,600 units, 75% completed | | $100,965* |
    *Direct materials (10,600 × $7.2) | $76,320 | |
    Conversion (10,600 × 75% × $3.1) | 24,645 | |
| $100,965 | |
Materials added during January from Weaving Department, 163,200units | | $1,199,520 |
Direct labor for January | | 229,536 |
Factory overhead for January | | 280,544 |
Goods finished during January (includes goods in process,January 1), 165,200 units | | — |
Work in process, January 31, 8,600 units, 25% completed | | — |
a. Prepare a cost of production report for theCutting Department. If an amount is zero or a blank, enter in \"0\".For the cost per equivalent unit computations, round your answersto two decimal places.
Karachi Carpet Company |
Cost of Production Report-Cutting Department |
For the Month Ended January 31 |
Unit Information |
Units charged to production: |
Inventory in process, January 1 | |
Received from Weaving Department | |
Total units accounted for by the CuttingDepartment | |
Units to be assigned costs: |
| | Equivalent Units |
| Whole Units | Direct Materials | Conversion |
Inventory in process, January 1 | | | |
Started and completed in January | | | |
Transferred to finished goods in January | | | |
Inventory in process, January 31 | | | |
Total units to be assigned cost | | | |
Cost Information |
Cost per equivalent unit: |
| Direct Materials | Conversion |
Total costs for January in Cutting Department | $ | $ |
Total equivalent units | | |
Cost per equivalent unit | $ | $ |
Costs assigned to production: |
| Direct Materials | Conversion | Total |
Inventory in process, January 1 | | | $ |
Costs incurred in January | | | |
Total costs accounted for by the CuttingDepartment | | | $ |
Costs allocated to completed and partiallycompleted units: | | | |
Inventory in process, January 1 balance | | | $ |
To complete inventory in process, January 1 | $ | $ | |
Cost of completed January 1 work in process | | | $ |
Started and completed in January | $ | | |
Transferred to finished goods in January | | | $ |
Inventory in process, January 31 | | | |
Total costs assigned by the Cutting Department | | | $ |
| | | |
Feedback
b. Compute and evaluate the change in cost perequivalent unit for direct materials and conversion from theprevious month (December). If required, round your answers to twodecimal places.
| Increase or Decrease | Amount |
Change in direct materials cost per equivalent unit | | $ |
Change in conversion cost per equivalent unit | | $ |