Construction bids for the Spruce Street Project were opened and evaluated. A bid in the...

70.2K

Verified Solution

Question

Accounting

Construction bids for the Spruce Street Project were opened and evaluated. A bid in the amount of $1,500,000 was accepted, and the contract, bearing a 4 percent retention clause was signed in October 2014.

Required: Record this transaction in the Street Improvement Fund.

Answer & Explanation Solved by verified expert