Construct the following network(AOA) and determine the minimumtotal cost to complete the project if indirect cost is Rs.1500 perday.
Activity
NT
CT
NC
CC
1-2
6
4
6000
7800
1-3
7
3000
4200
2-3
1
5000
9200
2-5
5
7500
3-4
3
2000
6800
4-5
4000
4-6
5600
5-6
4100