Consider the following information: Costs Activity (hours) $ 51,00040,000...

80.2K

Verified Solution

Question

Accounting

Consider the following information:
Costs Activity (hours)
$ 51,00040,000
$ 50,00041,000
$ 58,00042,000
$ 56,00043,000
What cost and activity would be used as the high data point in high-low cost estimation?
Multiple Choice
None of these.
$58,000 and 42,000 hours
$58,000 and 43,000 hours
$56,000 and 43,000 hours
$56,000 and 42,000 hours

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students