Compute the capacity (bottleneck rate) in jobs per hour (jph) of the following configurations and record...

90.2K

Verified Solution

Question

General Management

Compute the capacity (bottleneck rate) in jobs per hour (jph) ofthe following configurations and record your numerical answers (inorder) to the nearest tenth of jph. (Enter numbers only):

a. A station with two (2) machines operating in parallel with5-minute process times (te) at each machine.

b. A balanced line with two (2) series single-machine stations,both with average processing times (te) of 10 minutes.

c. A line with four (4) single machine stations in series, wherethe average processing times are:

15, 18, 10, & 12 minutes respectively.

d. A four (4) station line with multi-machine stations A, B, C,& D, where the number of parallel machines are 2, 6 10, & 4respectively. The average processing times (te) at each station are10, 24, 40, & 18 minutes respectively (see table below).

Process Line with series stations & parallelmachines per station Question (d)

Station

te(minutes)

te(hours)

Machine jph(1/te)

Machines/ station

Station jph

A

10

2

B

24

6

C

40

10

D

18

4

Minimum rate (rb) =

Answer & Explanation Solved by verified expert
4.4 Ratings (596 Votes)
a A station with two 2 machines operating in parallel with5minute process times te at each machineno of machines2cycle timemachine5mincapacity per machine12partshoursince we have 2 machines processing 12 partshourtotal    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students