Collins Co. had an unfavorable direct-labor efficiency variance of $5,250. The actual wage rate was...

60.1K

Verified Solution

Question

Accounting

Collins Co. had an unfavorable direct-labor efficiency variance of $5,250. The actual wage rate was $0.50 more than the standard rate of $10.00. If the company's standard direct-labor hours allowed for actual production totaled 9,000 hours, compute the actual direct-labor hours worked.