Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities...

Free

70.2K

Verified Solution

Question

Accounting

Calculating Activity-Based Costing Overhead Rates

Assume that manufacturing overhead for Goldratt Company consistedof the following activities and costs:

Setup (1,000 setup hours)$150,000
Production scheduling (400 batches)80,000
Production engineering (60 change orders)60,000
Supervision (2,000 direct labor hours)66,000
Machine maintenance (12,000 machine hours)48,000
Total activity costs$404,000

The following additional data were provided for Job 845:

Direct materials costs$7,000
Direct labor cost (5 Milling direct labor hours;35 Finishingdirect labor hours)$1,000
Setup hours5 hours
Production scheduling1 batch
Machine hours used (25 Milling machine hours;5 Finishingmachine hours)30 hours
Production engineering3 change orders

(a) Calculate the cost per unit of activity driver for eachactivity cost category.
Setup
$Answer


Production scheduling
$Answer
Production engineering
$Answer
Supervision
$Answer
Machine maintenance
$Answer

(b) Calculate the cost of Job 845 using ABC to assign the overheadcosts.
$Answer

(c) Calculate the cost of Job 845 using the plantwide overhead ratebased on machine hours. (Round your answer to the nearestdollar.)
$Answer

(d) Calculate the cost of Job 845 using a machine hour departmentaloverhead rate for the Milling Department ($27 per hour) and adirect hour overhead rate for the Finishing Department ($97 perhour). (Round your answer to the nearest dollar.)  
$Answer

Answer & Explanation Solved by verified expert
4.4 Ratings (923 Votes)

Solution a:

Computation of Activity rates
Activity cost pool Overhead costs Cost drivers Activity Rate
Setup $1,50,000 1000 $150.00 per setup hour
Production scheduling $80,000 400 $200.00 per batch
Production engineering $60,000 60 $1,000.00 per change order
Supervision $66,000 2000 $33.00 per DLH
Machine maintenance $48,000 12000 $4.00 per Machine hour

Solution b:

Computation of Overhead assigned to Job 845
Activity Activity Rate Cost Driver used Overhead Allocated
Setup $150.00 5 $750
Production scheduling $200.00 1 $200
Production engineering $1,000.00 3 $3,000
Supervision $33.00 40 $1,320
Machine maintenance $4.00 30 $120
Total Cost assigned $5,390
Computation of Cost of Job 845 (Using ABC)
Direct material cost $7,000
Direct labor cost $1,000
Overhead assigned $5,390
Total Cost of Job 845 $13,390

Solution c:

Computation of Cost of Job 845 (Using Plantwide rate)
Direct material cost $7,000
Direct labor cost $1,000
Overhead assigned ($404000/12000*30) $1,010
Total Cost of Job 845 $9,010

Solution d:

Computation of Cost of Job 845 (Using Departmental rate)
Direct material cost $7,000
Direct labor cost $1,000
Overhead assigned ($27*25 + $97*5)) $1,160
Total Cost of Job 845 $9,160

Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students