Calculate the Pay-off Period for an IS project that has a $200,000 development cost in year...

90.2K

Verified Solution

Question

Finance

Calculate the Pay-off Period for an IS project that has a$200,000 development cost in year 1 and annual $40,000 maintenancecosts from year 2 onwards. The benefits are expected to be $100,000in Year 2 and growing $25,000 a year as adoption of the systemincreases. The discount rate is 0%.

Answer & Explanation Solved by verified expert
4.3 Ratings (807 Votes)
Calculation of payoff period for an IS project Explaination As the project life is not given in the problem it is assumed that it has unlimited usual life    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

Calculate the Pay-off Period for an IS project that has a$200,000 development cost in year 1 and annual $40,000 maintenancecosts from year 2 onwards. The benefits are expected to be $100,000in Year 2 and growing $25,000 a year as adoption of the systemincreases. The discount rate is 0%.

Other questions asked by students