Calculate the labor efficiency variance:
Labor costs:
Budgeted costs (per unit)2.25 hours at 16.40 per hour based on 350 units.
Actual:
Units: 310
Hours: 620
Labor cost: 10,540
a.1,435 favourable
b.1,271 favourable
c.899 favourable
d.1,435 adverse

Answer & Explanation Solved by verified expert