Calculate the fully loaded cost of labor for the project team using the following data....

90.2K

Verified Solution

Question

Accounting

Calculate the fully loaded cost of labor for the project team using the following data. What is the direct cost of labor? What is the fully
loaded cost of labor?
Worker Hours
needed
Overhead
charge
Personal
charge
Hourly
rate
Sara 401.751.12 $27
Peter 601.301.08 $20
Ray 301.751.12 $48

Answer & Explanation Solved by verified expert