both questions please QUESTION 21 Assume the earned value (EV) is...

60.1K

Verified Solution

Question

Finance

both questions please
image
QUESTION 21 Assume the earned value (EV) is 100 and actual cost (AC) is 200. What is the cost performance index? 50% 100% None of these answers are correct 200% QUESTION 22 Please calculate the schedule performance index (SPD) given the following information Planned Value (PV) - 80: Earned Value (EV) - 100 80% 120% Unable to be determined 125%

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students