Bob Carlton's golf camp estimates the following workforce requirements for its services over the next...

70.2K

Verified Solution

Question

Accounting

Bob Carlton's golf camp estimates the following workforce requirements for its services over the next two years:

Quarter

1

2

3

4

5

6

7

8

Demand (hrs)

4,200

6,400

3,100

5,000

4,600

6,400

3,600

4,800

Each certified instructor puts in 480 hours per quarter regular time and can work an additional 120 hours overtime. Regular-time wages and benefits cost Carlton $7,200 per employee per quarter for regular time worked up to 480 hours, with an overtime cost of $20 per hour. Unused regular time for certified instructors is paid at $15 per hour. There is no cost for unused overtime capacity. The cost of hiring, training, and certifying a new employee is $10,000. Layoff costs are $4,000 per employee. Currently 8 employees work in this capacity.

a. Find a workforce plan using the level strategy that allows for no delay in service. It should rely only on overtime and the minimum amount of undertime necessary. What is the total cost of the plan?

b. Use a chase strategy that varies the workforce level without using overtime or undertime. What is the total cost of this plan?

c. Consider the following proposed plan for a different demand scenario. In this case, each certified instructor puts in 480 hours per quarter regular time. All other cost and capacity values are the same as above.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students