Blossom Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.3 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract:

2019 2020 2021
Costs incurred during the year $623,000 $806,000 $675,900
Estimated costs to complete 1,487,000 671,000 0

Calculate the gross profit to be recognized each year using the completed-contract method.

2019 2020 2021
Revenue $

$

$

Expenses

Gross Profit $

$

$

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students