BlayCo's standard and actual costs per unit for the most recentperiod, during which 600...

50.1K

Verified Solution

Question

Accounting

BlayCo's standard and actual costs per unit for the most recentperiod, during which 600 units were actually produced, are givenbelow:

Standard Quantity/Hours:  Materials- 4 feet per unit,Labor -unit 2 hours, VariableMOH- 2 hours per unit

Standard Price/Rate:Materials $2.00 per feet,Labor-$8.00foot per hour, VariableMOH- $3.00 per hour

Actual Quantity/Hours: Materials-1,000 feet, Labor-800 hours, VariableMOH- 800 hours

Actual Total Cost: Materials-$1,500,Labor-$4,000, VariableMOH-$2,000

Required (show your work): From the foregoing information,compute the following variances. Show whether the variance isfavorable (F) or unfavorable (U):

Thank you.

Answer & Explanation Solved by verified expert
4.4 Ratings (803 Votes)
Solution All the variances are calculated as below Direct Material Price Variance Actual Price 1500 1000 feet 150 per foot Standard Price 200 per foot Variance or Difference in Price 050 per foot x Actual Quantity PURCHASEDUSED 1000 foot Direct Material Price Variance 500 Favorable Direct Material QuantityEfficiencyUsage Variance Standard Quantity Allowed for actual production Actual ProductionActivity 600 Units x Allowed Standard    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

In: AccountingBlayCo's standard and actual costs per unit for the most recentperiod, during which 600 units...BlayCo's standard and actual costs per unit for the most recentperiod, during which 600 units were actually produced, are givenbelow:Standard Quantity/Hours:  Materials- 4 feet per unit,Labor -unit 2 hours, VariableMOH- 2 hours per unitStandard Price/Rate:Materials $2.00 per feet,Labor-$8.00foot per hour, VariableMOH- $3.00 per hourActual Quantity/Hours: Materials-1,000 feet, Labor-800 hours, VariableMOH- 800 hoursActual Total Cost: Materials-$1,500,Labor-$4,000, VariableMOH-$2,000Required (show your work): From the foregoing information,compute the following variances. Show whether the variance isfavorable (F) or unfavorable (U):Thank you.

Other questions asked by students