Below is data captured from last week’s production numbers on machining center AG-03: Scheduled operation = 10...

70.2K

Verified Solution

Question

General Management

Below is data captured from last week’s production numbers onmachining center AG-03:

Scheduled operation = 10 hours per shift, 1 shift, 5 days perweek

Lunch = 30 minutes per day

Breaks = Two 15 minutes per day

Morning Huddle Meeting = 10 minutes per day

Planned 5S Activities = 5 minutes per day

Planned Maintenance = 25minutes per week

Standard cycle time = 0.5 minutes per unit

Below is the Operator Downtime Log Sheet for the Week onMachining Center AG-03

Day

Event

Time (min)

Monday

Setup

75

Material Shortage

20

Sensor Blocked

15

Tuesday

Maintenance Repair

120

Setup

90

Jam

10

Jam

15

Jam

10

Wednesday

Setup

60

Sensor Blocked

15

Thursday

Breakdown

240

Setup

70

Insert/ Wearable Tooling Replacement

15

Friday

Setup

115

Sensor Blocked

15

Below is the Operator Production Log Sheet for the Week onMachining Center AG-03

Day

Total Quantity Produced

Defects

Monday

738

45

Tuesday

495

28

Wednesday

791

18

Thursday

360

35

Friday

690

26

Total

3074

152

Calculate OEE for the week (5 days) using the data provided.Show all work.

What is your assessment of the current situation?

What specific steps would you take to improve OEE?

Answer & Explanation Solved by verified expert
4.3 Ratings (727 Votes)
Monday OEE DATA Shift Length Minutes 600 a Number of Shifts 1 b Short Breaks per Shift Minutes Each Minutes 15 Nb 2 Total 30 c Meal Break per Shift Minutes Each Minutes 45 Nb 1 Total 45 d Down Time Minutes 115 e Ideal Rate PiecesHour 120 PiecesMinute 2 f Total Pieces Produced per Shift 738 g Rejected Pieces per Shift 45 h OEE VARIABLES CALCULATION Planned Production Time Minutes 525 i acdb Operating Time Minutes 410 j ieb Good Pieces per Shift 693 k gh OEE FACTORS CALCULATION Availability 781 900 l ji Performance 900 950 m gfj Quality 939 999 n kg Overall OEE 660 854 o lmn Tuesday OEE DATA Shift Length Minutes 600 a Number of Shifts 1 b Short Breaks per Shift Minutes Each Minutes 15 Nb 2 Total 30 c Meal Break per Shift    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students