Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days...

80.2K

Verified Solution

Question

Operations Management

Below are the data for a Time-Cost CPM Scheduling modelanalysis. The time is in days and the costs include both direct andindirect costs. If you crash this project to reduce the total timeby two days what is the total time of the project and total cost?Explain. (Note: Cut and paste your Precedence diagram.)

Activity

Immediate

Predecessor

Normal Time

Crash Time

Normal Cost

Crash Cost

A

None

3

2

200

400

B

A

4

3

300

600

C

A

1

---

400

---

D

B and C

3

2

200

250

E

D

2

1

500

600

F

E

2

---

600

---

G

E

3

1

300

450

H

G

1

---

400

---

Answer & Explanation Solved by verified expert
4.2 Ratings (615 Votes)
Based on the given data we find the crash cost per day as shownbelowThe formula for calculating crash cost per day is shown in thetableTotal Normal Cost of the project 2900Based on the predecessor relationship we prepare projectnetwork diagram as shown belowThe above network diagram in the form of formulas is shown belowfor better understanding and referenceThe above    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students