Based on past experience, a manufacturing process requires 4.5 hours of direct labour for each...

80.2K

Verified Solution

Question

Accounting

Based on past experience, a manufacturing process requires 4.5 hours of direct labour for each $3000 worth of raw materials processed. If the company is planning to consume $150,500 worth of raw materials, what total amount should it budget for labour at $27.50 per hour?

Answer & Explanation Solved by verified expert