At the beginning of 2017 Atlantic Yachts enters into a contract to build a luxury...

50.1K

Verified Solution

Question

Accounting

At the beginning of 2017 Atlantic Yachts enters into a contract to build a luxury yacht for a customer that is expected to take three years to complete. The contract price is $12,000,000. Completion is scheduled for the end of 2019. Atlantics year end is December 31. The following is a year by year summary of construction costs incurred and the estimated costs to complete the projects at the end of each year.

2017 2018 2019

Actual costs incurred current year $2,250,000 $6,750,000 $2,325,000

Actual costs incurred prior years -0- $2,250,000 $9,000,000

Cumulative actual costs incurred to date $2,250,000 $9,000,000 $11,325,000

Estimated costs to complete end of year $6,750,000 $2,250,000 -0-

Total Costs $9,000,000 $11,250,000 $11,325,000

Billings $2,100,000 $7,800,000 $2,100,000

Cash Collections $1,500,000 $6,000,000 $4,500,000

Required: Prepare the entries under the completed-contract method for 2017

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students