Assuming $5,000 indirect cost per month, and 12% markup. If the owner retains 7.5% of validated progress payments until the project is completed, and payments will be billed at the end of the month and will be received one month later. Leo construction also needs to pay the bank 1% per month for the amount of the overdraft at the end of the month. How much Leo Construction is expected to receive from owner at month 3?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students