Assume you are the project manager of a project. The planned schedule is as follows....

80.2K

Verified Solution

Question

Accounting

  1. Assume you are the project manager of a project. The planned schedule is as follows. Each phase is planned to be completed one after the other. Today is the end of June. (20 points)

Task

Scheduled

Duration

Budget

Project Planning

January

1 month

$8, 000

Requirement

February and March

2 months

$16, 000

Design

April

1 month

$10, 000

Coding

May and June

2 months

$22, 000

Testing

July and August

2 months

$20, 000

(1) use the project status chart, calculate the following values.

At the end of June,

Task

Status at the end of June

Project Planning

Complete, spent $5,000

Requirement

Complete, spent $14,000

Design

Complete, spent $12,000

Coding

50% Complete, spent $12,000

Testing

Not yet started

Value

Show the calculation

Answer

PV(BCWS)

EV(BCWP)

AC(ACWP)

(2) Describe current budget and schedule situation (e.g. over budget? behind schedule?).

Budget:

Schedule:

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students