Assume you are the Design/Build Contractor for a CVS Pharmacy inLogan, OH. The building is 11,945 square feet in size withconstruction scheduled to commence on January 18, 2017. Use theprogress completion schedule from a similar CVS Pharmacy in Athens,OH, to organize the overall schedule for the project by weeklyprogress for a completion date (turn over to owner) on May 23,2017.
1. Progress in one week: awnings, landscaping, permanent electricalpower, gas service
2. Progress in two weeks: compactor pad poured with concrete, drivethrough poured with concrete, water line, dumpster pad
3. Progress in two weeks: drywall finishing, painting, electricalrough-in, glass and glazing
4. Progress in two weeks: pharmacy window and pneumatic tube,flooring, lights, ceiling tiles
5. Progress in three weeks: demolition, clear and grub site,excavation and erosion control
6. Progress in two weeks: block cleaning, transformer set, basecoat of paving
7. Progress in two weeks: exterior wall block, irrigation, grading,demo for turning lanes
8. Progress in one week: footers, column pads, curb layout, parkinglot layout, site grading
9. Progress in two weeks: interior framing, doors and hardware,window frames, electrical rough-in, plumbing rough-in
10. Progress in two weeks: interior slab, block work, stormsewer
11. Progress in one week: landscaping, exterior signage, parkinglot striping, site clean-up, project completion
12. Progress in one week: millwork, lights, electrical finish,plumbing finish, HVAC finish
13. Progress in two weeks: sanitary pump station, service panelsset, sidewalks poured, stone base for pavement
14. Progress in two weeks: steel erection, exterior framing, HVACroof curbs, roofing, concrete curb, sanitary sewer, relocatetelephone lines, parking lot light conduit