Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is...

80.2K

Verified Solution

Question

Civil Engineering

Assume you are the Design/Build Contractor for a CVS Pharmacy inLogan, OH. The building is 11,945 square feet in size withconstruction scheduled to commence on January 18, 2017. Use theprogress completion schedule from a similar CVS Pharmacy in Athens,OH, to organize the overall schedule for the project by weeklyprogress for a completion date (turn over to owner) on May 23,2017.
1. Progress in one week: awnings, landscaping, permanent electricalpower, gas service
2. Progress in two weeks: compactor pad poured with concrete, drivethrough poured with concrete, water line, dumpster pad
3. Progress in two weeks: drywall finishing, painting, electricalrough-in, glass and glazing
4. Progress in two weeks: pharmacy window and pneumatic tube,flooring, lights, ceiling tiles
5. Progress in three weeks: demolition, clear and grub site,excavation and erosion control
6. Progress in two weeks: block cleaning, transformer set, basecoat of paving
7. Progress in two weeks: exterior wall block, irrigation, grading,demo for turning lanes
8. Progress in one week: footers, column pads, curb layout, parkinglot layout, site grading
9. Progress in two weeks: interior framing, doors and hardware,window frames, electrical rough-in, plumbing rough-in
10. Progress in two weeks: interior slab, block work, stormsewer
11. Progress in one week: landscaping, exterior signage, parkinglot striping, site clean-up, project completion
12. Progress in one week: millwork, lights, electrical finish,plumbing finish, HVAC finish
13. Progress in two weeks: sanitary pump station, service panelsset, sidewalks poured, stone base for pavement
14. Progress in two weeks: steel erection, exterior framing, HVACroof curbs, roofing, concrete curb, sanitary sewer, relocatetelephone lines, parking lot light conduit

Answer & Explanation Solved by verified expert
4.1 Ratings (436 Votes)
As a contractor for CVS Pharmacy I will do the activities in the following order 1Progress in two weeks exterior wall block irrigation grading demo for turning lanes Initially we need to give a boundary of the site so that all the activities take place with the boundary and no legal problem arises We also have to watch out for water supplies required for various activites taking place in site and also make way for the vehicles like truck for stoppage and truning activities 2Progress in three weeks demolition    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students