Accounting
Assume the following information: Actual run time this week 4,500 minutes Machine time available this week 5,000 minutes Actual run rate this week 3.6 units per minute Ideal run rate 4.0 units per minute Defect-free output this week 11,000 units Total output this week (including defects) 16,200 units The quality rate is closest to: Multiple Choice 0.65. 0.68. 0.54. 0.60