Assume that you are the project manager for the construction ofa 15-mile road. Further assume that the work is uniformlydistributed over 12 weeks. The total approved budget for thisproject is $600,000. At the end of the first three weeks of work$160,000 has been spent and five miles of road have been completed.At the end of the first three weeks, what do you think of thecurrent status of the project in terms of cost and schedule?Describe the earned value analysis terms that you use and theirformulas, and then calculate each metric. Then interpret yourresults. Important: there are more than 3 earned value metrics tocalculate.

Answer & Explanation Solved by verified expert
4.0 Ratings (562 Votes)
Please please please LIKE THIS ANSWER so that I can get a small benefit Please EV BAC x work completedtotal work required EV 600000 x 5 mi15 mi 200000 PV BAC x time passedtotal schedule time    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students