Aspen Technologies has the following budget data: Estimated direct labor hours 11,100 ...

80.2K

Verified Solution

Question

Accounting

Aspen Technologies has the following budget data:

Estimated direct labor hours 11,100
Estimated direct labor dollars $63,800
Estimated factory overhead costs $166,200

If factory overhead is to be applied based on direct labor hours, the predetermined overhead rate is

a. $22.46

b. $14.97

c. $11.98

d. $17.97

Answer & Explanation Solved by verified expert