As part of the Project Scope Statement of a house construction project, prepare the detailed Milestone Schedule...

50.1K

Verified Solution

Question

Mechanical Engineering

As part of the Project Scope Statement of a house constructionproject, prepare the detailed
Milestone Schedule (Baseline Milestone – Date) by arranging thefollowing activity
items/milestones in a proper sequence from No. 1 to 15, assumingthe first milestone date as 05-
01-2020 and the last as 30-09-2020. Assume the dates in betweencorresponding to the various
milestones which are given in no particular order: Foundationcomplete, Excavation complete,
Permits approved & construction begins, Contract signed, Designcomplete, Framing complete,
Roofing complete, Architectural design started, Final inspectionand acceptance by Owners,

Interior finish, Exterior finish, Landscaping complete, HVACsystem installed, Plumbing-
electrical-mechanical passed, Plumbing-electrical-mechanicalinstalled.

Answer & Explanation Solved by verified expert
3.7 Ratings (347 Votes)
Note Im not sure about excavation It can be 2nd activity as below or 7th activity Usually during excavation soil testing load bearing capacity of site is studied and building is designed accordingly This step may vary country to country as per regulation Also few activities can be done simultaneously The very first thing will be contract signing    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students