As of end of month, $50,000 of work on Project was scheduled to be completed....

90.2K

Verified Solution

Question

Finance

As of end of month, $50,000 of work on Project was scheduled to be completed. However, only 80% of the work had been completed.

  • AC =$52,000 BAC=$100,000 ETC=$45,000
  1. What is the Earned Value of the work completed (round to nearest whole number)?

Answer & Explanation Solved by verified expert