Question

Accounting

Arthur Corporation used regression analysis to predict the annual cost of indirect materials. The results were as follows: Indirect Materials Cost Explained by Units Produced

Constant $23000
Standard error of Y estimate $500
R2 0.743
Number of observations 645
X coefficient(s) 23
Standard error of coefficient(s) 1.7

If the company expects to produce 15,000 units, what is the estimated cost of indirect materials?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students