Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated...

60.1K

Verified Solution

Question

Accounting

Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information:

Activity Cost Driver Amount M XY
Production setups Number of setups $ 79,000 16 24
Material handling Number of parts 58,000 64 16
Packaging costs Number of units 300,500 105,000 70,000
$ 437,500

What is the total overhead allocated to Product M using the current system?

Multiple Choice

$258,300.

$300,500.

$262,500.

$179,200.

Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information:

Activity Cost Driver Amount M XY
Production setups Number of setups $ 87,000 16 24
Material handling Number of parts 54,000 51 34
Packaging costs Number of units 192,500 70,000 40,000
$ 333,500

What is the total overhead per unit allocated to Product XY using activity-based costing (ABC)?

Multiple Choice

$2.71.

$3.53.

$3.60.

$3.03.

Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information:

Activity Cost Driver Amount M XY
Production setups Number of setups $ 72,000 12 28
Material handling Number of parts 50,000 54 36
Packaging costs Number of units 355,000 108,000 72,000
$ 477,000

What is the total overhead allocated to Product XY using the current system?

Multiple Choice

$264,600.

$190,800.

$212,400.

$286,200.

Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information:

Activity Cost Driver Amount M XY
Production setups Number of setups $ 84,000 8 12
Material handling Number of parts 42,000 56 24
Packaging costs Number of units 211,500 90,000 60,000
$ 337,500

What is the total overhead per unit allocated to Product M using activity-based costing (ABC)?

Multiple Choice

$2.25.

$2.10.

$2.11.

$2.46.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students