Verified Solution

Question

Operations Management

Agile Project Management andScrum

3. What do you need to make estimates as a team using“Estimation Poker”?

4. How do you resolve differences in estimation with “EstimationPoker”?

5. When should you use affinity estimating and how aredifferences in estimates resolved?

Answer & Explanation Solved by verified expert
4.0 Ratings (413 Votes)
3 While making estimates following are needed product owners answers questions raised by estimators moderator to take notes on the discussion understand conduct the Estimation Poker process description of the user story for which estimation is being    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students