Adjust your analysis to the information in the table without modifying the baseline information. Analyze the...

50.1K

Verified Solution

Question

General Management

Adjust your analysis to the information in the table withoutmodifying the baseline information. Analyze the project executiontime following the PERT Diagram methodology. Establish CriticalPath of the project. Set the duration of the work. Complete thetable.

ActivityDescription of ActivityPredecessorDurationEarliest TimeLatest Time
AConstruction Permit-3
BMobilizationA2
CTopographyA4
DWall Type AB, C12
EWall Type B and CB,C45
FFoundationsB,C20
GElectricityF6
HStructureD,G22
ITouch-UpsH30
JRoofH10
KPaintI18
LTrials and DeliveryE,K3

Answer & Explanation Solved by verified expert
3.8 Ratings (336 Votes)
    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students