Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this...

60.1K

Verified Solution

Question

General Management

ActivityPredecessorOptimisticMost LikelyPessimistic
A4710
B2910
CA,B258
DC161928
EC6924
FE1713
GC41028
HD,F2514
IG,F5817
JH,I258
  1. Determine the expected completiontime for each activity.
  2. Construct the AON network for theactivities of this contract and determine the critical path for theproject.

Answer & Explanation Solved by verified expert
3.9 Ratings (461 Votes)
Expected time of each activityActivitytotmtpteto4tmtp62tpto62A471071B29108178C25851D161928204E6924119F171374G410281216H251464I5181715674J25851The earliest and latest expected time for each activity iscalculated by considering the expected time teActivityImmediate    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students