Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and...

70.2K

Verified Solution

Question

Civil Engineering

Activities, predecessors and duration for a School BuildingProject

Activity

Description

Immediate predecessor

Duration (days)

A

Clear Site and mobilize labour and equipment

None

5

B

Excavate foundation

A

15

C

Procure materials (sand, cement, chippings etc.)

A

10

D

Pour foundation concrete

B, C

5

E

Mould sandcrete blocks (substructure)

C

5

F

Construct substructure block work

D, E

15

G

Construct superstructure block work

F, H

30

H

Make doors and window frames

I

10

I

Procure and preserve roof timber

C

10

J

Roofing, plastering and painting

G, I

25

K

Fabricate roof trusses

I

15

L

Mould sandcrete blocks (superstructure)

C

10

  1. Draw the network diagram.
  2. What is the critical path of the above project?
  3. Calculate the total and free floats for the activities.

Answer & Explanation Solved by verified expert
3.9 Ratings (586 Votes)
For each noncriticalactivity the total float and free float calculations areshown in    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students