A worker under the halsey method of remuneration has a day rate of Rs 12
per week of 48 hours, plus a cost of living bonus of 10 paise per hour worked. He
is given an 8 hour task to perform, which the accomplishes in 6 hours. He is
allowed 30% of the time saved as premium bonus. What would be his total hourly
rate of earnings, and what difference would it make if he was paid under the
Rowan method?