A supplier for the automobile industry manufactures car andtruck frames at two different plants. How many hours should eachplant be scheduled to operate to exactly fill each of the orders inthe table? The production rates (in frames per hour) for each plantare given in the first table (on the left side).
Plant Car Frames Truck Frames
A 6 6
B 7 3
Orders
1 2 3
Car frames 1732 1150 1917
Truck frames 1236 676 1257
Complete the table below:
Orders
1 2 3
Number of hours for plant A ______ ______ ______
Number of hours for plant B ______ ______ _______