A software project is very close to its deadline,but is running behind schedule.Without intervention it is...

50.1K

Verified Solution

Question

Operations Management

A software project is very close to its deadline,but is runningbehind schedule.Without intervention it is expected to be late andthis will not be acceptable. The project manager has been told thatmanagement are prepared to provide additional resources (fundsand/or software developers) to get the project completed ontime.

The project manager is considering options to get the projectcompleted by the deadline.

One option is to assignadditional software developers to thetasks on the critical paths.

  1. Is this a good option? Discuss the advantages and disadvantagesof this option.

Describe another option that the project manger should consider.Discuss the advantages and disadvantages of this alternativeapproach.

Answer & Explanation Solved by verified expert
4.5 Ratings (923 Votes)
Answer 1 Assigning additional software developer on the critical path will be a good option is based on the the analysis of the reason for delay and then taking the decision accordingly Advantage    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students