A project manager, in preparation for the construction of roads, has identified the activities and their durations...

90.2K

Verified Solution

Question

General Management

A project manager,in preparation for the construction of roads, has identified theactivities and their durations to prepare a difficult stretch ofmotorway (as in the following table).

Activity

Duration (days)

Precedingactivities

A

5

B

10

C

1

D

8

B

E

10

B

F

9

B

G

3

A, D

H

7

A, D

J

3

F

K

8

E, H

L

4

C, J

  1. How long the project will take?   
  2. State the critical activities.   
  3. If activity A is delayed for 10 days, what is the effect on theproject duration?   

Answer & Explanation Solved by verified expert
4.5 Ratings (782 Votes)
Project networkFormulaa Project duration    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students