A project for improving a billing process has the followingprecedence relationships and activity? times: Using the info belowcalculate the slack for each activity. Which activities are on thecriticalpath?????????????????????????????????????????????????????????????????????????????????????????????????????????  

Activity

Activity Time? (weeks)

Immediate? Predecessor(s)

A

5

----

B

10

-----

C

6

A

D

14

?B, C

E

9

B

F

5

D

G

3

E

H

6

?F, G

Answer & Explanation Solved by verified expert
3.9 Ratings (770 Votes)
Computation ofearliest starting and finishing times is aided by two simplerules1 The earliest finish timefor any activity is equal to its earliest start time plus itsexpectedduration tEF ES t2 ES for activities at nodeswith one entering arrow is equal to EF of the    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students