Question
Accounting
a permit is obtained on friday aug 1, the material are to be delivered aug 8the material are needed labor begins on aug 11 it is estimated 15 days of labor are required the crew will work everyday including weekends and holidays the project is scheduled to be completed on sep 8. how many floating days are available for this project?
the material are needed labor begins on aug 11
it is estimated 15 days of labor are required
the crew will work everyday including weekends and holidays
the project is scheduled to be completed on sep 8.
how many floating days are available for this project?
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.