A particular single-machine workstation has a capacity of 1,000 units per day and variability is moderate,...

90.2K

Verified Solution

Question

General Management

A particular single-machine workstation has a capacity of 1,000units per day and variability is moderate, such that V = (SCV ofarrivals + SCV of effective process time)/2 = 1. Demand iscurrently 900 units per day. Suppose management has decided thatcycle times should be no longer than 1.5 times the average processtime.

A) What is the current cycle time in multiples of the processtime? (i.e. if the current cycle time was 2 times longer than theprocess time, put 2 in the answer box)

B) If variability is not changed, what would the daily capacityhave to be in order to meet the requirement that average cycle timebe no longer than 1.5 times process time?

C) If capacity is not changed, what value would be needed for Vin order to meet the requirement that average cycle time be nolonger than 1.5 times process time?

Answer & Explanation Solved by verified expert
3.6 Ratings (346 Votes)
Here is the answer I hope it helps youplease rate it Answer Interarrival time a 1900 day Raw process time p 11000 0001 day Variability V 1 Utilization u pa 110001900 09 Average    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students