A new wastewater treatment plant was built to treat the wastewater flow 800,000 gpd. The capital...

70.2K

Verified Solution

Question

Chemistry

A new wastewater treatment plant was built to treat thewastewater flow 800,000 gpd. The capital cost to build thewastewater treatment plant was $6,000,000. The annual operation andmaintenance costs of operating the plant is $700,000/year. Estimatethe cost of treating 1000 gallons of wastewater ($/1000 gallon).Assume the design life as 20 years and interest rate of 4%.

Answer & Explanation Solved by verified expert
3.6 Ratings (266 Votes)
Wastewater treatment plant capacity 800000 gpd Design life 20 years Interest rate 4 Capital cost 6000000 Annual maintenance 700000years Total cost of plant for 20 years Capital cost interest cost for 20    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students