A firm expects to use 6 pounds of materials per unit of output but ends...

50.1K

Verified Solution

Question

Accounting

A firm expects to use 6 pounds of materials per unit of output but ends up using 5 pounds per unit of output. The firm actually produced 20,000 units of output but had only expected to produce 18,000 units of output. What is the standard amount of direct materials (SQ).

100,000

108,000

120,000

90,000

Answer & Explanation Solved by verified expert