A construction projectis carried out by a general contractor with the followingdescriptions:

  • Project Duration: 3 months(Start: May 1st; End: July 31st)
  • Contract Amount:20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181
  • Budget Amount:100,936+200,081+300,685
  • Contract Terms and Conditions
    • Materials: The constructioncompany pays material suppliers in full when it receives paymentfrom the owner. On the last day of each month the constructioncompany may bill the owner for the work completed during the month.The owner pays the monthly bills one month after they arereceived.
    • Labor: The construction companypays for labor on the 25th of each month.
    • Subcontractor: The constructioncompany pays subcontractors when it receives payment from the ownerbut withholds 5% from the subcontractor’s payment. Final paymentwill include payment of the retention.
    • Between the contractor and theowner: On the last day of each month the construction company maybill the owner for the work completed during the month. The ownerpays the monthly bills one month after they are received. The ownerwithholds 5% from the construction company's payment. Final paymentwill include payment of the retention.
  • Cost-loaded schedule and billingschedule to the owner
MonthMayJuneJuly
Cost-LoadedSchedule  Materials20,71330,08150,630
Labor40,97860,88670,089
Subcontractor30,500100,165152,181
Bill to Owner100,936200,081300,685

What is the amount ofcash to maintain a positive cash flow in this project?

Answer & Explanation Solved by verified expert
4.1 Ratings (689 Votes)
Assumption 1 The contracting company bills the owner on 30th of the month and the owner receives the bill on the same day and therefore makes the payment on the 30th of the next month The key here is the labor payment which    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

A construction projectis carried out by a general contractor with the followingdescriptions:Project Duration: 3 months(Start: May 1st; End: July 31st)Contract Amount:20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181Budget Amount:100,936+200,081+300,685Contract Terms and ConditionsMaterials: The constructioncompany pays material suppliers in full when it receives paymentfrom the owner. On the last day of each month the constructioncompany may bill the owner for the work completed during the month.The owner pays the monthly bills one month after they arereceived.Labor: The construction companypays for labor on the 25th of each month.Subcontractor: The constructioncompany pays subcontractors when it receives payment from the ownerbut withholds 5% from the subcontractor’s payment. Final paymentwill include payment of the retention.Between the contractor and theowner: On the last day of each month the construction company maybill the owner for the work completed during the month. The ownerpays the monthly bills one month after they are received. The ownerwithholds 5% from the construction company's payment. Final paymentwill include payment of the retention.Cost-loaded schedule and billingschedule to the ownerMonthMayJuneJulyCost-LoadedSchedule  Materials20,71330,08150,630Labor40,97860,88670,089Subcontractor30,500100,165152,181Bill to Owner100,936200,081300,685What is the amount ofcash to maintain a positive cash flow in this project?

Other questions asked by students