Question

Mechanical Engineering

A Company has set up a weighted scoring matrix forevaluation of a three potential projects. Below are the weightedproject scores of the three projects :

  • Project A : The weighted projectscores = 115
  • Project B : The weighted projectscores = 99
  • Project C : The weighted projectscores = 75

Using the weighted project scores,which project should be the company firstpriority?

Answer & Explanation Solved by verified expert
3.6 Ratings (645 Votes)

Weighted project scores of the three projects :

  • Project A : The weighted project scores = 115
  • Project B : The weighted project scores = 99
  • Project C : The weighted project scores = 75

In weighted scoring matrix for evaluation, the project with higher weighage is given first priority and the project with lowest score is given least priority.

From the given data Project A has highest weighted scores of 115 compared to other 2 projects. Hence Project A should be the first priority of the company and  Project C should be the last priority of the company .


Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students